- Cryogenic tank.
- Cryogenic tanks (stationary).
- Evaporators.
- Reduction-measuring station, odorization, boiler room (gas heating).
- Factory boiler room.
SCHEDULE OF IMPLEMENTATION OF LNG STATION WITH DIVISION OF TASKS AND THEIR IMPLEMENTATION TIME:
- Obtainment of a map for design purposes, 2-3 weeks.
- Applying for a housing development decision, 2 days after receiving the map.
- Submission of the application for environmental conditions, 3 days after receiving the map.
- Obtaining a housing development and environmental decision, 2-3 months.
- Development of a technical project, obtaining a construction permission, 6 weeks after receiving the decision.
- Purchase and delivery of LNG facility equipment, 6 months from the agreement on cooperation.
In conclusion, the time of implementation of the LNG regasification station, including all concessions and decisions, is about 7 months.