Installation of LNG regasification station

img-barter

  1. Cryogenic tank.
  2. Cryogenic tanks (stationary).
  3. Evaporators.
  4. Reduction-measuring station, odorization, boiler room (gas heating).
  5. Factory boiler room.

 

SCHEDULE OF IMPLEMENTATION OF LNG STATION WITH DIVISION OF TASKS AND THEIR IMPLEMENTATION TIME:

  • Obtainment of a map for design purposes, 2-3 weeks.
  • Applying for a housing development decision, 2 days after receiving the map.
  • Submission of the application for environmental conditions, 3 days after receiving the map.
  • Obtaining a housing development and environmental decision, 2-3 months.
  • Development of a technical project, obtaining a construction permission, 6 weeks after receiving the decision.
  • Purchase and delivery of LNG facility equipment, 6 months from the agreement on cooperation.

In conclusion, the time of implementation of the LNG regasification station, including all concessions and decisions, is about 7 months.